Forging new factory completed foundation
Page view
[Abstract]:
July 29, 2013, under construction in forging the new plant was officially completed foundation works, forging new factory building is needed in order to meet current sales, increase forged aluminum forging production line capacity expansion. Forging new plant broke ground in May this year, is hereby o testing center building, covering an area of about 1,500 square meters, according to plan, the new equipment will be in August expanded into the plant, forging a whole new plant will be completed in September this year to complete, and at the end of October to complete the entire layout of the workshop and formally put into production.